UAE e-invoicing deadlines: which phase is your business in and when must you go live?
UAE e-invoicing starts on 1 January 2027 for businesses with Revenue of AED 50 million or more, and on 1 July 2027 for smaller businesses. Find your phase and dates.

Quick answer
UAE e-invoicing is mandatory in phases. Businesses with Revenue of AED 50 million or more had to appoint an Accredited Service Provider (ASP) by 30 October 2026 and must go live on 1 January 2027. Businesses below AED 50 million must appoint an ASP by 31 March 2027 and go live on 1 July 2027. Government entities follow on 1 October 2027. As of November 2026, no postponement has been announced.
Key takeaways
- The phase test is Revenue of AED 50,000,000: a business at exactly AED 50 million or above is in the first phase, because Ministerial Decision No. 244 of 2025 says “equal to or exceeds”.
- Revenue means gross income for the most recent accounting period as shown in the financial statements. It is not VAT turnover.
- The first-phase ASP deadline moved from 31 July 2026 to 30 October 2026 under Ministerial Decision No. 66 of 2026. Some pages still print 31 July or 31 October, and both are wrong.
- Go-live stayed at 1 January 2027 for the first phase. As of November 2026, the UAE Ministry of Finance has announced no postponement.
- The ASP-appointment date is itself enforceable: Cabinet Decision No. 173 of 2026 penalises failure to implement, including failure to appoint an ASP, at AED 5,000 plus AED 5,000 for each month or part of a month, capped at AED 50,000 in any 12 consecutive months.
- Once live, VAT-registered businesses issue a tax invoice within 14 days of supply; since 1 October 2026, businesses not registered for VAT have 14 Business Days from the Date of Business Transaction.
What are the UAE e-invoicing deadlines?
The UAE e-invoicing deadlines depend on a business’s size. Under Ministerial Decision No. 244 of 2025, as amended by Ministerial Decision No. 66 of 2026, businesses with Revenue of AED 50 million or more go live on 1 January 2027, other businesses on 1 July 2027, and Government Entities on 1 October 2027. The table shows each group’s two dates as of November 2026.
| Group | Appoint an ASP by | Go live by | Status as of November 2026 |
|---|---|---|---|
| Revenue of AED 50 million or more (first phase) | 30 October 2026 | 1 January 2027 | ASP date has passed; go-live not postponed |
| Revenue below AED 50 million (second phase) | 31 March 2027 | 1 July 2027 | Dates unchanged |
| Government Entities (no revenue test) | 31 March 2027 | 1 October 2027 | Dates unchanged |
| Pilot programme (invited, written consent) | Not applicable | Began 1 July 2026 | Open only to businesses the UAE Ministry of Finance (MoF) notified |
| Voluntary adopters (any business) | Not applicable | Allowed from 1 July 2026 | No penalties while the use is voluntary |
| Transactions inside one VAT group | Not applicable | Excluded for 24 months from 1 January 2027 | Temporary exclusion under Ministerial Decision No. 197 of 2026 |
The first-phase ASP date, 30 October 2026, has passed; the other dates are still ahead. The UAE e-invoicing guide explains the whole system; this post covers only dates.
The VAT-group row is a timing relief, not a permanent exclusion. The MoF’s guidelines call it a grace period that “affects the timing of compliance only”. No official end date has been published, so treat the 24 months as running from 1 January 2027 and check the decision text before relying on a specific end date.
How is the AED 50 million Revenue threshold measured?
The AED 50 million threshold is measured on Revenue, which Ministerial Decision No. 244 of 2025 defines as “the gross income earned by a Person during the most recent Accounting Period”. The figure comes from the financial statements prepared under UAE law or, if none exist, other documents the Federal Tax Authority (FTA) accepts.
Revenue is therefore an accounting figure. It is not VAT turnover and it is not the value of taxable supplies on a VAT return. A transport company should read the income line of its latest financial statements, not its VAT filings.
Is exactly AED 50 million in the first phase?
A business with Revenue of exactly AED 50 million is in the first phase. Ministerial Decision No. 66 of 2026 applies the first-phase dates to a Person whose Revenue “is equal to or exceeds AED 50,000,000”, and the second phase covers Revenue “less than AED 50,000,000”.
The MoF press release of 10 May 2026 says “exceed”. The decision text governs, and it includes the equal-to case. The FTA’s release of 25 October 2026 uses “equal or exceed”.
What about new companies and corporate groups?
For a newly established company, an MoF programme presentation from October 2026 uses projected revenue for the ongoing financial year. That is guidance, not legislation. Group revenue is a separate question: the decision measures Revenue per “Person”, and the MoF’s FAQ leaves group treatment to the business and its accountants or auditors.
Which phase is my business in?
A business’s phase follows from three facts: whether it is a Government Entity, whether it sells only to consumers, and its Revenue against AED 50 million. The decision table below applies the rules in Ministerial Decisions No. 243 and No. 244 of 2025 as amended. Businesses in scope but unsure can read who must comply with UAE e-invoicing.
| Your situation | Phase | Appoint ASP by | Go live by |
|---|---|---|---|
| Revenue of AED 50,000,000 or more | First phase | 30 October 2026 (passed) | 1 January 2027 |
| Revenue below AED 50,000,000 | Second phase | 31 March 2027 | 1 July 2027 |
| Government Entity | Government phase, no revenue test | 31 March 2027 | 1 October 2027 |
| Government body acting in a sovereign capacity that does not compete with the private sector | Excluded | Not applicable | Not applicable |
| Sells only to consumers (B2C) | Outside the system for those sales until the Minister decides otherwise | Not applicable for those sales | Not applicable for those sales |
| Sells only to consumers but buys from other businesses | Own phase, as a recipient | Per Revenue, as above | Per Revenue, as above |
The consumer-only rows come from Ministerial Decision No. 244 of 2025, Article 5(2), and the FTA’s FAQ. The FTA FAQ states that a business making only B2C supplies, but receiving supplies from other businesses, must still appoint an ASP and implement the system. No decision bringing B2C into the system had been issued as of November 2026.
Was the large-business ASP deadline 31 July, 30 October or 31 October 2026?
The first-phase ASP deadline was 30 October 2026. Ministerial Decision No. 66 of 2026 moved it from 31 July 2026, and the MoF announced the change on 10 May 2026. The decision was issued on 6 May 2026, according to the FTA’s consolidated text. Go-live stayed on 1 January 2027.
Two other dates circulate. The original 31 July 2026 date is outdated. The MoF’s Guidelines Version 2.0 of 26 October 2026 print “31st October 2026” in a table, which is an inconsistency inside official guidance. The decision governs, and the FTA’s release of 25 October 2026 also says “no later than 30 October 2026”.
Missing the date has a cost. Cabinet Decision No. 173 of 2026, item 1, fines failure to implement the system “including the failure to appoint an Accredited Service Provider”. The UAE e-invoicing penalties post sets out the amounts.
Has the 1 January 2027 go-live been postponed?
The 1 January 2027 go-live has not been postponed as of 22 November 2026. The MoF said on 27 September 2026 that “as of now” the mandatory first-phase date “remains unchanged”, and it had announced no change in the weeks since.
In its June 2026 programme presentation, the MoF called the Ministerial Decision No. 66 change “a targeted and final adjustment” and wrote that “no further extensions will be granted”. That is a statement of intent from one date. It does not promise that the date can never change.
Readers who plan around a deadline should re-check the legislative list on the MoF e-invoicing page and the MoF and FTA news pages before relying on any date. The MoF describes its portal as the official source of information on e-invoicing in the UAE.
What must second-phase businesses do by 31 March and 1 July 2027?
Businesses with Revenue below AED 50 million must do two things: appoint an ASP by 31 March 2027 and implement e-invoicing by 1 July 2027. Ministerial Decision No. 66 of 2026 replaced only the first-phase paragraph, so these dates are unchanged as of November 2026.
| Date | Requirement | Source | Consequence if missed |
|---|---|---|---|
| From 1 July 2026 | Optional: start voluntarily | Ministerial Decision No. 244 of 2025, Article 4 | None: Cabinet Decision No. 173 of 2026 does not apply to voluntary use |
| 31 March 2027 | Appoint an ASP | Ministerial Decision No. 244 of 2025, Article 5(1)(b) | Exposure to the failure-to-implement penalty, which covers failure to appoint an ASP |
| 1 July 2027 | Implement the system and send and receive e-invoices | Ministerial Decision No. 244 of 2025, Article 5(1)(b) | AED 5,000 for the first instance, then AED 5,000 for each month or part of a month, capped at AED 50,000 in any 12 consecutive months |
Exposure can start at the ASP date, months before go-live. Cabinet Decision No. 173 of 2026 excludes voluntary users, but once a business is in a mandatory phase, item 1 covers failure to appoint an ASP. The MoF’s guidelines state penalties apply from the date a business must implement, which is ambiguous, so the cautious reading is to treat 31 March 2027 as binding.
A second-phase business is not idle until 2027. From 1 January 2027, first-phase suppliers will send it e-invoices, and the buyer’s onboarding status does not change the supplier’s duty. The step-by-step implementation plan covers the project work between now and the deadline.
When do government entities and their suppliers go live?
Government Entities must appoint an ASP by 31 March 2027 and go live by 1 October 2027, with no revenue test. Ministerial Decision No. 244 of 2025, Article 5(1)(c), sets both dates. Government bodies acting in a sovereign capacity that does not compete with the private sector are excluded under Ministerial Decision No. 243 of 2025.
Businesses that sell to government follow their own phase, not the government’s. The MoF’s guidelines state that a customer’s onboarding status “does not affect the Electronic Invoicing obligations in respect of a Business Transaction”, and that supplies to Government Entities are subject to e-invoicing.
Until a government buyer is live, the supplier also sends a regular tax invoice, such as a PDF, and addresses the e-invoice to the predefined endpoint 0235:9900000098. This is the guidelines’ rule for any buyer that has not yet implemented e-invoicing. A first-phase transport company invoicing a ministry in early 2027 should plan for both documents.
Which recurring deadlines apply once you are live?
Once live, a business has recurring deadlines for issuing e-invoices and for telling its ASP about changes. The issuing deadline depends on VAT registration: VAT-registered Issuers follow the VAT law’s timeline, and Issuers not registered for VAT have 14 Business Days. The table lists each deadline and its source.
| Situation | Deadline | Source |
|---|---|---|
| VAT-registered Issuer: tax invoice | Within 14 days of the date of supply | Ministerial Decision No. 243 of 2025, Article 6(4); VAT Decree-Law, Article 67(1) |
| VAT-registered Issuer: summary tax invoice | Within 14 days of the end of the calendar month | VAT Executive Regulation, Article 59(13) |
| Issuer not registered for VAT | Within 14 Business Days of the Date of Business Transaction, since 1 October 2026 | Ministerial Decision No. 243 of 2025, Article 6(5), as replaced by Ministerial Decision No. 197 of 2026 |
| Change to details registered with the FTA | Notify the ASP in writing within 5 Business Days of the FTA’s confirmation | Ministerial Decision No. 243 of 2025, Article 5(3) |
The Date of Business Transaction is the earlier of the date the transaction occurred and the date payment was received. A Business Day is any day except weekends and official federal-government holidays. VAT registrants should note that the VAT law says “14 days”, not business days.
Late notice of a data change is fined under Cabinet Decision No. 173 of 2026 at AED 250 for each day of delay, up to AED 5,000 per calendar month. As of November 2026, the Minister had not set a legal deadline for the ASP’s reporting to the FTA, which happens in parallel with delivery.
Frequently asked questions
Does revenue from other companies in our group count toward the AED 50 million test?
No official rule says that group revenue counts toward the AED 50 million test, and the MoF has not ruled on it as of November 2026. Ministerial Decision No. 244 of 2025 measures Revenue for each “Person”, meaning each legal person. The MoF’s FAQ says the treatment of revenue within a wider corporate group should be assessed by the reporting entity and its accountants or auditors. Take advice before assuming a subsidiary is in the second phase.
Which accounting period counts as the “most recent” one?
The decision defines Revenue as gross income for the most recent Accounting Period, which is the period for which the business must prepare financial statements. No official reference date fixes which period counts as most recent. In practice, businesses use their latest financial statements, and the FTA can accept other documents if none exist.
Why do some MoF press releases say revenue that “exceeds” AED 50 million?
The MoF’s 10 May 2026 press release simplified the wording to “exceed”. The decision text says “equal to or exceeds”, so a business with Revenue of exactly AED 50 million is in the first phase. When a press release and a ministerial decision differ, the decision governs, and the FTA’s 25 October 2026 release uses “equal or exceed”.
Who took part in the UAE e-invoicing pilot programme?
The pilot programme began on 1 July 2026 and is limited to businesses that the MoF notified and that agreed in writing to take part, called the Taxpayer Working Group. As of November 2026, the MoF has not published a participant count, a list of participants or an end date for the pilot. Any business has also been allowed to start voluntarily since the same date.
What changes on 1 January 2027 for a smaller business that buys from first-phase companies?
A smaller business’s own deadlines stay at 31 March and 1 July 2027, but its suppliers in the first phase start e-invoicing on 1 January 2027. The MoF’s guidelines require a supplier to send a regular tax invoice, such as a PDF, as well as the e-invoice until the buyer is live. Input VAT recovery depends on retaining the invoice in e-invoice form where one is required or issued.